Los Angeles Department of Water and Power
Delivery Process: Construction Management-at-Risk
Construction Type:: New Construction
Total Square Footage: 27,100 SF Total
This project was part of a repowering project at the Scattergood Generating Station for the City of Los Angeles. Caliente constructed one of three buildings in addition to a metal warehouse and pre-manufactured guardhouse on the grounds of this station. The Control Building is a 20,000 SF, ground-up four-story steel structure with slab on deck, exterior metal panels and a membrane roof. The 6,660 SF pre-manufactured metal warehouse and 500 SF pre-manufactured guardhouse were also constructed simultaneously.